Thursday, October 11, 2012

SARSAS General Meeting Agenda for Monday, October 22, 2012 OPEN TO THE PUBLIC

Monday, October 22, 2012
175 Fulweiler Avenue (the Domes), Auburn, CA 95603 
Contact: Jack Sanchez at 530-888-0281
Meetings are Fourth Monday of each month at 10-11 a.m.

I.      Self- introductions and sign-ins.       

II.    SARSAS Philosophy–We believe by working together with many individuals and agencies at the same table, we can achieve the mission of SARSAS, which is to return salmon and  steelhead to the entire 33 mile length of the Auburn Ravine
.
III   Featured speaker is Mary Tappel, Beaver Management Expert, “Beaver Management in our New Age of Returning Salmon”

IV. Gary Mapa, Vice President of SARSAS, “For the Good of the Order”

Scheduled Speakers:
                                                               
November 26, 2012, Lincoln   Regional Sewer Project Manager Dave Lee, “Regional Sewer Project – an Update”

Tuesday, December 18, 2012, Mark Egbert, District Manager, El Dorado County and Georgetown Divide Resource Conservation Districts, “Restoration of a Reservoir”

January 28, 2013, Richard Rivas, Natural Resources Conservation Services, Wildlife Biologist, “WHIP and Fish
Passage”

February 25, 2013, Ron Ott, SARSAS Fish Passage Specialist, “Fish Screens on Area Streams and Rivers”

March 25, 2013, Placer County Sheriff Edward N. Bonner, “Fishing Stories of a Boy Growing Up in Loomis”

April 22, 2013, Einar Maisch, PCWA Director of Strategic Affairs, “Middle Fork Authority Update”

May 28, TUESDAY, 2013, Rocko Brown, ESA PWA, Restore Salmon Ecosystems”

June 24. 2013, Jack Sales, International Dark-Sky Association, “Salmon and Light Pollution”


July 22, 2013, TBA
August 26, 2013, TBA

September 23, 2013, Randy Hansen, SARSAS Fish Friendly Farming Coordinator, “Fish Friendly Farming Update”

Tuesday, October 9, 2012

Auburn Ravine Fish Passage Project on NID's Lincoln Gauging Station Completed December 2011

Fish Passage Project

Lincoln, California

A Watershed ImprovemIrrigation District (NID)ent Project of The Nevada

In 2010, residents and fishermen in Lincoln, Placer County, witnessed a phenomenon not seen in years. At least 30 fall run Chinook salmon were counted in Auburn Ravine Creek inside Lincoln city limits.
Several small modifications to downstream irrigation water diversion points in Sutter and Placer counties had allowed the salmon to migrate from the Central Valley as high as Lincoln (elev. 167 ft.). However, continued migration of the fish to higher spawning grounds was hampered by a growing waterfall, caused by tail water erosion below a water measurement station.
The station is owned and operated by the Grass Valley, Nevada County-based Nevada Irrigation District (NID) and has been used since 1981 to chart water flows from NID to other nearby agencies.
Soon the possibility of bringing more natural conditions back to Auburn Ravine came into wider public focus. The fish passage concept had originated a few years earlier when the Auburn Ravine-Coon Creek Restoration Plan was adopted as part of the Placer County Conservation Plan.
Through a series of meetings, NID and Placer County worked out preliminary details of a project that would allow fish migration at any flow level over and through the six-foot barrier at the water measurement station and the eroded creek bed below it. The goal was to bring a more natural condition to Auburn Ravine. The collaborative effort would become known the Auburn Ravine Fish Passage Project.
The project drew wide industry and community support. Placer County secured a CALFED grant that would fund part of the project, NID took the role of lead agency and pledged further funding. Soon the Dry Creek Conservancy and Granite Bay Flycasters were on board with additional funds.
Project planning and environmental studies were completed in early 2011, and construction was scheduled to begin in the fall of 2011. Needed water deliveries and the potential for early fall storms left a narrow window for streambed construction so a very tight construction schedule was developed.
Another construction concern was that the project, located in the Lincoln Crossing Nature Preserve, is surrounded by homes and used by residents for walks and outdoor enjoyment. NID addressed issues of access, noise, dust and safety to the satisfaction of neighbors. Meanwhile, the district worked to keep costs down and the project on schedule and eligible for its CALFED funding.
Construction was scheduled for Oct. 1-Nov. 30, 2011 and Sacramento contractor Preston Pipelines, Inc. was brought on board to do the job. Complexities in stream construction led to a lengthy and detailed state and federal permitting process, with final permitting obtained just in time.
During the narrow two-month construction window, a temporary bypass was constructed to dry the creek bed for the work while continuing the required downstream flows. “There are risks involved in creek bed construction at this time of year,” said NID Project Engineer Keane Sommers. “We were very concerned about rainwater coming down the creek and flooding our construction site so we oversized the bypass.”
Once the bypass was in place, 200 feet of the overgrown, eroded creek channel was cleared and tapered back to a more natural form. A “nature-like fish way” with a series of rock chutes and step pools was sculpted into the streambed. Concrete cutoff walls designed to stem erosion were buried up to 13 feet into the channel and stabilized by large rock and smaller materials. Native plants were added to the newly-reconfigured steam banks and surrounding areas were restored to pre-construction conditions. NID will monitor the site for the next five years to ensure that the grasses and 125 trees that were planted provide a suitable riparian habitat.
Dry weather through much of the fall of 2011 allowed the project to move forward without delay. Creek work was completed by the November 30, 2011 deadline.
The project received accolades from nearby residents as well as from fishing and environmental advocates who are enthusiastic about opening an additional mile of Auburn Ravine to fish movement. SARSAS President Jack Sanchez said he was confident the project would lead to more fish migration and said he looked forward to conducting fish counts this coming fall. Upstream, in Auburn, city officials see the project as an initial step in a long term vision of opening Auburn Ravine all the way to their city, which they see as a potential educational and economic boost the Placer County seat.
“Watershed stewardship is an important part of our mission,” said NID General Manager Ron Nelson, who is former Chairman of ACWA’s Region 3. “We have a watershed improvement fund and this was a community effort that fit our mission well.”
The Auburn Ravine Fish Passage Project was completed for $865,000. NID contributed $491,000, CALFED $304,000, Placer County $50,000, Bella Vista Foundation $10,000, and Granite Bay Flycasters $10,000